May 28, 2022The BarnMORE KITCHEN AND THE FINISH LINEWith the hard work with the kitchen done (units, plumbing, electrics) the finish line was now finally and genuinely in sight. The...
May 11, 2022The MillA SLIGHT CHANGE OF PLANWhile phase 1 was being completed we had been thinking a lot about our design for the extending of the mill and were getting increasingly...
Apr 11, 2022The BarnSTARTING THE KITCHEN INSTALLThe last major job on the interior of the barn was the installation of the kitchen. In the recent past I had fitted two kitchens and on...
Mar 23, 2022The BarnDECORATING BEGINS & BATHROOMS GO INAfter another lengthy break from the project (while we undertook phase 1 of the mill project) the focus finally returned to the barn and...
Feb 4, 2022The MillAND... PHASE 1 IS COMPLETEOnce the roof was completed externally the ceiling needed reinstating inside the top bedroom. As we had effectively moved the roof up by...